This Containerized Demineralised Water Treatment plant was recently manufactured and shipped to a Power Station in Victoria.
After engaging with the client and using our knowledge and experience in executing water treatment plants within the Australian Power Sector, our highly skilled sales personnel we were able to demonstrate to the client that an Early Contractor Involvement (ECI) model would be the best way forward in delivering the plant in time. The client engaged us under an ECI contract, which enabled rapid preliminary engineering and selections to be made in a collaborative environment, resulting into well researched and mutually acceptable price, to deliver this fast-track project.
Osmoflo team went on to execute the project, complete the site install and commissioning, to the agreed time schedule. The system is now ready to support the upcoming high demand period in summers.
Osmoflo has also received confirmation on the contract for on-going operations and maintenance support for the facility.